Johnson's rule

In operations research Johnson's rule is a method of scheduling jobs in two work centers. Its primary objective is to find an optimal sequence of jobs to reduce makespan (the total amount of time it takes to complete all jobs). It also reduces the amount of idle time between the two work centers. The method minimizes the makespan in the case of two work centers. Furthermore, the method finds the shortest makespan in the case of three work centers if additional constrains are met.[1]

The technique requires several preconditions:

Johnson's rule is as follows:

  1. List the jobs and their times at each work center.
  2. Select the job with the shortest activity time. If that activity time is for the first work center, then schedule the job first. If that activity time is for the second work center then schedule the job last. Break ties arbitrarily.
  3. Eliminate the shortest job from further consideration.
  4. Repeat steps 2 and 3, working towards the center of the job schedule until all jobs have been scheduled.

Given significant idle time at the second work center (from waiting for the job to be finished at the first work center), job splitting may be used.

Example

Each of five jobs needs to go through work center A and B. Find the optimum sequence of jobs using Johnson's rule.

Job times (hours)
Job Work center A Work center B
A 3.2 4.2
B 4.7 1.5
C 2.2 5.0
D 5.8 4.0
E 3.1 2.8

1. The smallest time is located in Job B (1.5 hours). Since the time is in Work Center B, schedule this job last. Eliminate Job B from further consideration.

? ? ? ? B

2. The next smallest time is located in Job C (2.2 hours). Since the time is in Work Center A, schedule this job first. Eliminate Job C from further consideration.

C ? ? ? B

3. The next smallest time after that is located in Job E (2.8 hours). Since the time is in Work Center B, schedule this job last. Eliminate Job E from further consideration.

C ? ? E B

4. The next smallest time after is located in Job A (3.2 hours). Since the time is in Work Center A, schedule this job first. Eliminate Job A from further consideration.

C A ? E B

5. The only job left to consider is Job D.

C A D E B

Notes

  1. Johnson, S. M. (1954). "Optimal Two- and Three-Stage Production Schedules With Set-up Time Included" (PDF). Naval Research Logistics Quarterly. 1: 61–68. Retrieved 7 September 2013.

References

Further reading

This article is issued from Wikipedia - version of the 9/22/2016. The text is available under the Creative Commons Attribution/Share Alike but additional terms may apply for the media files.