Kori Nuclear Power Plant

Kori Nuclear Power Plant

Kori Nuclear Power Plant, Reactors Kori 1, Kori 2, Kori 3, Kori 4 from right to left.
Location of Kori Nuclear Power Plant in South Korea
Country South Korea
Location Gori, Busan
Coordinates 35°19′12″N 129°17′24″E / 35.319904°N 129.290053°E / 35.319904; 129.290053Coordinates: 35°19′12″N 129°17′24″E / 35.319904°N 129.290053°E / 35.319904; 129.290053
Status Operational
Commission date 1978
Operator(s) Korea Hydro & Nuclear Power
Nuclear power station
Reactor type PWR
Reactor supplier Westinghouse
KEPCO E&C
Cooling source Sea of Japan
(East sea of Korea)
Cooling towers no
Power generation
Units operational 1 X 576 MWe
1 X 640 MWe
2 x 997.5 MWe
2 X 1,011.5 MWe
1 X 1,340 MWe
Make and model GEC Turbines (Rugby)
Doosan
Units under const. 1 X 1,340 MWe
Nameplate capacity 6,574 MW
Planned: 7,914 MW

The Kori Nuclear Power Plant (Korean: 고리원자력발전소, Hanja: 古里原子力發電所) is a South Korean nuclear power plant located in Kori, a suburban village in Busan. It is owned and operated by Korea Hydro & Nuclear Power, a subsidiary of KEPCO. The first reactor began commercial operation in 1978.

An expansion of the plant begun in 2006 added four new Korean-sourced reactors, the so-called Shin Kori reactors. The first pair of Shin Kori reactors are of the OPR-1000 design, while the second two are the APR-1400 design. By November 2010 the first was online and the rest undergoing trials or construction. Two further APR-1400 reactors are in planning.

Reactors

So far, all reactors on site are pressurized water reactors.

Name Net Electric Output First Criticality Commercial Start Reactor Supplier NSSS supplier Architecture Construction
Kori 1   576 MWe 06/1977 04/1978 Westinghouse GEC Turbines (Rugby) Gilbert Westinghouse
Kori 2   640 MWe 04/1983 07/1983 Westinghouse GEC Turbines (Rugby) Gilbert Westinghouse
Kori 3   1,011 MWe 01/1985 09/1985 Westinghouse GEC Turbines (Rugby) Bechtel Hyundai
Kori 4   1,012 MWe 10/1985 04/1986 Westinghouse GEC Turbines (Rugby) Bechtel Hyundai
Shin Kori 1   999 MWe 06/2010 02/2011 KHNP/KEPCO Doosan KOPEC Hyundai
Shin Kori 2   996 MWe 12/2011 07/2012 KHNP/KEPCO Doosan KOPEC Hyundai
Shin Kori 3 1,340 MWe  12/2015 mid 2016[1] KHNP/KEPCO Doosan KOPEC Hyundai
Shin Kori 4 1,340 MWe  early 2017[1] KHNP/KEPCO Doosan KOPEC Hyundai
Shin Kori 5[2] 1,340 MWe  Unknown Unknown Unknown Unknown Unknown
Shin Kori 6[2] 1,400 MWe  Unknown Unknown Unknown Unknown Unknown

(NSSS = nuclear steam supply system)

Incidents

On 9 February 2012 at 8:30 p.m. Kori 1 was shut down for regular inspections. After this the reactor lost all power for 12 minutes, and the diesel generator did not start. The reactor was to be inspected and the nuclear fuel was to be exchanged. According to the South Korean nuclear regulator all facilities for the spent-fuel-pool and the cooling of the reactor were still operational. The incident was not reported to the regulator before 12 March 2012.[3] The incident was graded at INES level 2.[4] Subsequently five senior engineers were charged for a coverup of the serious incident.[5]

On 2 October 2012 at 8:10 a.m. Shingori 1 was shut down after a warning signal indicated a malfunction in the control rod system. An investigation is currently underway to verify the exact cause of the problem.[6]

In June 2013 Kori 2 was shutdown, and Kori 1 ordered to remain offline, until safety-related control cabling with forged safety certificates is replaced.[7] Control cabling installed in the APR-1400s under construction failed flame and other tests, so need to be replaced delaying construction by up to a year.[8]

In October 2013 cable installed in Shin Kori 3 failed safety tests, including flame tests. Replacement with U.S. manufactured cable has delayed the startup of the plant.[8][9]

See also

References

  1. 1 2 "Fuel loading under way at Shin Kori 3". World Nuclear News. 4 November 2015. Retrieved 16 December 2015.
  2. 1 2 "NTI". Nuclear Threat Initiative.
  3. NHK-world (13 March 2012) S.Korean nuclear plant lost power for 12 minutes
  4. "Loss of shutdown cooling due to station blackout during refueling outage". IAEA. 23 April 2012. Retrieved 6 November 2012.
  5. "South Korea shuts nuclear reactors, warns of power shortages". AFP. Times of India. 5 November 2012. Retrieved 6 November 2012.
  6. Yonhap News (2 October 2012) Nuclear reactor halts operation due to malfunction
  7. "New component issues idle Korean reactors". World Nuclear News. 28 May 2013. Retrieved 7 June 2013.
  8. 1 2 "Recabling delays Shin Kori start ups". World Nuclear News. 18 October 2013. Retrieved 15 November 2013.
  9. "Shin-Kori 3 receives replacement cables". Nuclear Engineering International. 30 September 2014. Retrieved 10 March 2015.
This article is issued from Wikipedia - version of the 11/28/2016. The text is available under the Creative Commons Attribution/Share Alike but additional terms may apply for the media files.