Dan Ryan branch

Dan Ryan branch

A southbound Red Line train on its way to 95th
Overview
Type Rapid transit
System Chicago "L"
Status In Service
Locale Chicago, Illinois, United States
Termini CermakChinatown
95th/Dan Ryan
Stations 9
Services      Red Line
Daily ridership 45,355
(average weekday Feb. 2013)
Operation
Opened September 28, 1969
Operator(s) Chicago Transit Authority
Character Expressway median, Elevated
Rolling stock 5000-series
Technical
Line length 9.4 mi (15.1 km)
Track gauge 4 ft 8 12 in (1,435 mm)
Electrification Third rail, 600 V DC
Route map
Legend
Rock Island District
to LaSalle Street
State Street Subway

South Side Main Line
to Loop

South Side Main Line
to State Street Subway
17th Junction

Midway branch
to Midway

Federal Junction
Cermak Junction

Cermak–Chinatown

Exit 53C

I-55

I-90 / I-94

Sox–35th

Chicago Junction Railway

47th

Garfield

Jackson Park branch
to Cottage Grove

63rd

Englewood branch
to Ashland/63rd

Rock Island District
to Joliet

I-90

69th

79th

87th

95th/Dan Ryan

I-57

98th Yard

The Dan Ryan branch, or the South Red Line, is a 9.4 mi (15.1 km) long section of the Chicago "L" system located on the South Side of Chicago, Illinois. It is operated by the Chicago Transit Authority, as part of its Red Line service and is normally through-routed downtown; towards the North Side via the State Street Subway. As of February 2013, the branch serves (on average) 45,355 passengers per weekday.[1] As part of the CTA's busiest rapid transit line, it is operated 24 hours a day, 365 days a year. The branch serves the Chinatown, Armour Square, Fuller Park, Englewood, Greater Grand Crossing, Chatham and Roseland neighborhoods of Chicago, Illinois

The Dan Ryan Branch was shut down at 2 a.m. on May 19, 2013 and service to and from Howard via the State Street Subway was rerouted through the old 13th street portal onto the Green Line's South Side Main Line tracks to Garfield. After Garfield, the Red Line continued to the Englewood Branch of the Green Line, and terminated at Ashland/63rd until October 19, 2013. This was the old routing of the Howard-Englewood A of the North-South route from 1949 until 1993. On October 20, 2013, the branch reopened at 4 a.m.[2]

History

After World War II, the CTA built three new branches of the 'L' through the medians of freeways. The first was the Congress Branch, which opened on June 22, 1958. On July 30, 1958, proposals for a line in the median of the Dan Ryan Expressway and a line in the median of the Kennedy Expressway were among a series of projects proposed by the CTA.[3] The Dan Ryan Branch was built between 1967 and 1969 for a total cost of $38 million. When the branch opened on September 28, 1969, it was connected to the Lake Street Elevated via the Loop and the South Side Main Line. The branch was successful from the start, exceeding forecasts by 10%, and carrying an average of 99,000 passengers per day by the end of 1970. The opening of the Dan Ryan branch resulted in a decrease in ridership on the South Side Elevated and its two branches to Englewood and Jackson Park. On January 4, 1978, several large cracks were discovered under the elevated portion of the Dan Ryan Branch near Clark and 18th Streets. Service was suspended on this portion of the branch from January 4 to January 17, while repairs were being made.

On February 21, 1993, when the L routes were to be color-coded, the Dan Ryan branch became part of the present day Red Line. The CTA had decided that the Dan Ryan Branch's routing was inefficient due to the fact that the Dan Ryan Branch and North Side Main Line had a comparatively higher number of riders than the Lake Branch and South Side Elevated. On February 21, 1993, the Dan Ryan Branch was connected to the State Street Subway and the North Side Main Line with service to Howard, while the Lake Branch would be paired with the South Side Elevated and its Englewood and Jackson Park branches via The Loop. The Dan Ryan Branch connected to the State Street Subway via the subway's new extension to 16th and Wentworth, which was built from 1985 to 1990.

The Dan Ryan Branch initially used concrete railroad ties, but these were replaced by wooden ties after the concrete ties began to age more rapidly than expected. On April 17, 2004, the CTA began a $192,500,000 rehabilitation of the Dan Ryan Branch, which included installing a new signal system, replacing and upgrading substations, renovating platform canopies, and installing new elevators at the 47th and 69th stations.[4]

Red Line South Reconstruction

On November 3, 2011, local funding and $646 million in state funding was announced by Mayor Rahm Emanuel, Governor Pat Quinn, CTA President Forrest Claypool, several state lawmakers, and nearly a dozen aldermen, for a reconstruction project on the branch. Two options concerning the duration of construction were considered: A 5-month duration with no service the entire time or 4 years of weekend-only work. The choice of a 5-month duration with no service the entire time was ultimately chosen.[5]

On May 19, 2013, the Dan Ryan Branch was shut down at 2 a.m. as part of the Red Line South Reconstruction Project which cost $425 million.[5] With the branch being 44 years old, track conditions had been causing Red Line riders to experience longer travel times, overcrowded trains and less-reliable service. As part of the project, the Garfield, 63rd, and 87th stations were renovated and equipped with an elevator, making all Dan Ryan branch stations fully accessible for passengers with disabilities. The newly reconstructed Dan Ryan branch and the nine stations reopened on October 20, 2013 at 4 a.m.[6]

Extension

Dan Ryan extension

Legend
I-94

Dan Ryan
branch
UPRR

95th/Dan Ryan
I-57

98th Yard

103rd

111th

Michigan
130th
Between I-57 and Michigan alignment could be either
east or west of UPRR. Only east alignment shown.

Proposals are currently underway to extend the Red Line south from 95th Street. The CTA developed nine different proposed routes, one of which includes routing the Red Line down the median of the Bishop Ford Freeway and another in the median of Interstate 57. During an alternatives analysis meeting on April 11, 2007, CTA narrowed further study down to five possible routes, two for bus rapid transit and three for heavy rail (rapid) transit. The two bus routes would travel south from the 95th/Dan Ryan terminal either down Halsted Street or Michigan Avenue, while the heavy rail routes left for consideration were the Halsted and Michigan corridors (either underground or elevated) as well as the Union Pacific Railroad corridor (elevated or trench), which would traverse southeastward toward the South Shore Line. In October 2008 the CTA commissioned a $150,000-study of an extension due south to 130th/Stony Island in the community area of Riverdale.[7]

Alternatives

In December 2008, at the Screen 2 presentation of the federally mandated Alternatives Analysis Study, the possible corridors and modes of transit were furthered narrowed down to either Halsted Street (Bus Rapid Transit or elevated Heavy Rail Transit) and the Union Pacific Railroad corridor (elevated Heavy Rail Transit).[8]

In December 2009, the CTA identified the Locally Preferred Alternative as the Union Pacific corridor.[9] A map and description of the route are found here: Multiple Environmental Impact Studies will be carried out, and will determine exact alignments and design.[9][10]

The alignment consists of a new elevated rail line between 95th Street and a new terminal station at 130th Street, paralleling a Union Pacific Railroad line through the Far South Side neighborhoods of Roseland, West Pullman, and Riverdale. In addition to the terminal station at 130th, three new stations would be built at 103rd, 111th, and Michigan. Basic engineering, along with an environmental impact statement, are currently underway.[11]

Station listing

Dan Ryan Branch
Station Location Points of interest and notes
Cermak–Chinatown 138 W. Cermak Road Chinatown, McCormick Place, Chinatown Square, Chicago Public Library's Chinatown Branch
Sox–35th 142 W. 35th Street U.S. Cellular Field (formerly Comiskey Park), home of the Chicago White Sox, Illinois Institute of Technology, Armour Square, De La Salle Institute, Chicago Bee Building
47th 220 W. 47th Street Canaryville, DuSable High School, Fuller Park
Garfield 220 W. Garfield Boulevard Washington Park, Schulze Baking Company Plant, Raber House; Main connecting point for the University of Chicago and the Museum of Science and Industry
63rd 220 W. 63rd Street Urban Prep Charter Academy for Young Men, Englewood
69th 15 W. 69th Street Greater Grand Crossing, Paul Robeson High School, Yale Apartments
79th 15 W. 79th Street Chatham, Leo Catholic High School, Simeon Career Academy
87th 15 W. 87th Street Auburn Gresham, Chatham, Garden Homes Historic District
95th/Dan Ryan 15 W. 95th Street Roseland, Chicago State University, Trinity United Church of Christ, Carter G. Woodson Regional Library, Harlan Community Academy High School, Princeton Park, Fernwood

Proposed stations

Red Line extension
Station Location Points of interest and notes
103rd TBD Proposed station; Washington Heights, Percy L. Julian High School, Roseland
111th TBD Proposed station; Roseland, Fenger Academy High School
Michigan TBD Proposed station; West Pullman
130th TBD Proposed station; Altgeld Gardens, Riverdale, Carver Military Academy

Image gallery

External links

References

  1. "Ridership Report: February 2013" (PDF). Chicago Transit Authority. transitchicago.com. Retrieved April 8, 2013.
  2. "Red Line South Project Countdown until Completion Day!". Chicago Transit Authority. transitchicago.com. Retrieved October 8, 2013.
  3. Chicago Transit Authority Proposed $315,000,000, Twenty-Year Transit Expansion and Improvement Program Chicago Transit Authority. July 30, 1958. Accessed August 21, 2013
  4. Graham, Garfield. "Dan Ryan Branch". Chicago 'L'. chicago-l.org. Retrieved January 11, 2013.
  5. 1 2 "Red Line South Track Renewal Project". Chicago Transit Authority. Retrieved June 15, 2012.
  6. "Red Line South Project Countdown until Completion Day!". Chicago Transit Authority. transitchicago.com. Retrieved October 8, 2013.
  7. Regional Transit Authority (2008-10-03). "RTA Funded Study Looks at the Impact of the Proposed Red Line Extension" (PDF). Retrieved 2008-10-09.
  8. "Red Line Extension Alternatives Analysis Study" (PDF). Retrieved 6 January 2009.
  9. 1 2 "About the Project: Alternatives". Red Line Extension Project. Chicago Transit Authority. Retrieved December 17, 2009.
  10. "Project Schedule". Red Line Extension Project. Chicago Transit Authority. Retrieved December 17, 2009.
  11. "Red Line Extension Project". Chicago Transit Authority. Retrieved February 25, 2010.
This article is issued from Wikipedia - version of the 11/8/2016. The text is available under the Creative Commons Attribution/Share Alike but additional terms may apply for the media files.